Engagement phase of the project can be described as a meet-and-greet session between the client and United Power Technologies personnel. During this phase, both parties get familiar with each other business models and processes; client's general needs are discussed and areas of collaboration are discovered; and key stakeholders along with time and budget constraints are identified.
Tasks:
- Engage Sponsor
- Introduce UPT Process
- Identify Need(s), Key Stakeholders, Oversight, Budget
- Estimate Requirements Phase
- Phase After Action Review
Deliverables:
- Marketing Materials
- Project Governance and Structure Diagram
- Executive Summary / Business Plan
- Requirements Phase Project Plan
- Master Service Agreement
- Non Disclosure Agreement
- Requirements Phase Proposal
- Phase After Action Review Report
Participants:
- Sponsor
- UPT Engagement Manager
- UPT Solution Manager
|